[Task] process element

The [Perform task] process item is designed to create new activities in the system during process execution.

[Perform task] element setup

Specify task parameters on the element setup page (Fig. 8).

Fig. 8 The [Perform task] element setup page

chapter_process_designer_make_a_task.png 

Most element parameters, like [Subject], [Owner] or [Account], correspond to the fields on the activity page. If any parameter field is filled in, then when a process creates a new task, the corresponding field in the task page is automatically filled in. If the parameter is not filled in, then the corresponding field on the setup page will be blank and can be filled in manually.

You can fill in these fields using the parameter value window.

[Formula] – Enter the element caption. The caption is displayed on the process diagram. By default, the “Perform Task” caption is used.

[What should be done?] – enter the subject of the task. As a rule, the purpose of the task is indicated in this field. This is a required field.

[Task category] – Select the category of the new task, for example, “To do” or “Meeting”. This is a required field.

[Start in] – specify the time period after which the activity should start. The time can be specified in minutes, hours, days, weeks and months. This parameter is used to calculate the value in the [Start] field of the activity. This is a required field.

Note

The [Start] field of the activity is filled in with the [Start in] field value plus current user time. For example, if “30 minutes” is specified in the [Start in] field, and the task was created at 12:00, then “12:30” will be specified in the [Start] field of the created task.

[Planned duration] – enter the activity duration using minutes, hours, days, weeks or months. This parameter is used to fill in the [Due] field of the activity page. This is a required field.

Note

The [End] field of the activity setup page is filled in with the value from the [Start] field incremented by the value in the [Planned duration] field.

Select the [Show in calendar] checkbox to make the task appear in the [Calendar] view of the [Activities] section.

Note

If you do not select the [Show in calendar] checkbox, the activity will still be available in the [List] view of the [Activities] section.

[Show page automatically] – If the checkbox is selected, the activity execution page is displayed automatically as soon as the process initiates the activity.

[Owner] – Specify the user responsible for performing the task.

[Hint for user] – enter additional information about the task. The user will be able to view the hint by clicking the btn_com_information.png button on the activity page. The hint button is displayed on the displayed page.

[Remind in] – Indicate the time period for a reminder before the activity starts. When the specified time comes, the system will automatically create a notification for the corresponding employee.

[Connected to] – specify other system records that are connected to this task. As a result, the task will be added to the [Activities] detail of the corresponding record. By default, [Account] and [Contact] fields are displayed, but you can add fields to connect the task to other records by clicking the btn_button_connections.png button.

Note

In advanced mode, the element setup page contains additional parameters and connections with system records. The advanced mode is intended to be used by developers. Regular users are advised to use the regular mode of the element setup page.

Next

[Send email] process element

[User dialog] process item

[Open edit page] process element

[Auto-generated page] process item

[Pre-configured page] process element

[Call] process element

Did you find this information useful?